General Data: | USMC Design: | USMC Hullnumber: | Name of Ship: | |
EC2-S-C1 | MCE-476 | Betsy Ross | ||
Official Number or Navy Hull | Call Signal: | Flag: | Homeport: | |
243.156 | KKVE | US | San Francisco, California | |
Yard Number | Building Way or Basin: | Name of Building- or Conversion Yard: | ||
476 | 5 | Permanente Metals Corp.Richmond Yard No.2,Richmond,Ca |
Contract and Price Data: | Type of Contract: | Contract Price: | Final Price: | Difference between CP and FP: |
$0,00 | CP | $1.000.000,00 | $1.061.271,00 | +6.13% |
USMC Contract Number: | Contract Date: | Contract Delivery Date: | Named | |
MCc-2215 | 01-16-42 | 08-31-43 | 01-12-43 |
Building Data: | Laiddown/Start of Conversion: | Launched: | Delivered / Cancelled | Sponsor: | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02-20-43 12:00AM |
03-19-43 12:00AM |
03-31-43 12:00AM |
Mrs.B.F.Hodglin (wife of Vice-President and Manager of MacDonald & Kahn, Contractor) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Days on Way: | Days on Dock: | Days Total: | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
27 Days | 12 Days | 39 Days | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner: | Operator: | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
War Shipping Administration |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Comment: | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Builders trial completed on March 27th1943, sea trials successfully completed in San Francisco Bay and in Pacific Ocean on 29th 1943; |