General Data: | USMC Design: | USMC Hullnumber: | Name of Ship: | |
T1-M-BT1 | MC-2627 | Nodaway | ||
Official Number or Navy Hull | Call Signal: | Flag: | Homeport: | |
AOG-67 | US Navy | |||
Yard Number | Building Way or Basin: | Name of Building- or Conversion Yard: | ||
86 | 2 | St.John's River SB Co.,Jacksonville,Fl |
Contract and Price Data: | Type of Contract: | Contract Price: | Final Price: | Difference between CP and FP: |
$0,00 | CP | $1.230.000,00 | $1.022.203,48 | -16.89% |
USMC Contract Number: | Contract Date: | Contract Delivery Date: | Named | |
MCc-30837 | 07-26-44 | 03-26-45 | 12-04-45 |
Building Data: | Laiddown/Start of Conversion: | Launched: | Delivered / Cancelled | Sponsor: | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01-22-45 12:00AM |
04-14-45 12:00AM |
09-18-45 12:00AM |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Days on Way: | Days on Dock: | Days Total: | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
82 Days | 157 Days | 239 Days | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner: | Operator: | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
U.S.Department of Commerce |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Comment: | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Accepted incomplete By Commission (85.7%) for later disposal; |
Specification |